Pollution Control Agency
BAY WEST INC.
63186-15-25
PRP-FORMER TOWN AND COUNTRY OIL, LEAK 3807
{Empty}
complete investigation and construction work
Project Duration
Thu, 08/28/2014 - 00:00
Tue, 06/30/2015 - 00:00
Tue, 06/30/2015 - 00:00
Yes
{Empty}
Contract Amounts
$55560.00
{Empty}
$55560.00
Yes
Unknown
No
.
Lauralin Kania
lauralin.kani@state.mn.us
The contractor had excellent schedule maintenance and submitted all invoices on time. However, not all deliverables were received on time.
The contractor did a satisfactory job of adhering to program requirements, and showed improvement in this area. However, the reports generated were not always complete.
The contractor had satisfactory budget management.
Will engage contractor's services again but not on this project due to incompleteness of CCAD report and Pilot Test report (completed under separate work order). Contractor completed work under FY15 contract. Contractor was not asked to continue work on this project for FY16.
Yes
{Empty}
3 - neutral