Submission Number: 27445
Submission ID: 112351
Submission UUID: aee423f9-2c62-4406-aad2-f51275828f89

Created: Thu, 12/26/2024 - 17:49
Completed: Thu, 12/26/2024 - 17:49
Changed: Thu, 01/02/2025 - 15:04

Remote IP address: (unknown)
Submitted by: emily.nguyen
Language: English

Is draft: No

Locked: Yes
Commerce Dept
Siemens Industry, Inc.
240150
Energy Storage System Capacity Study
{Empty}
Legislation passed in 2023 (see Minnesota Sessions Laws 2023, Chapter 60 (HF2310), Article 12, Sec. 74) requires the Department of Commerce to produce a study of the energy storage system capacity required to achieve the state renewable energy standard and carbon-free goals under Minnesota Statutes, section 216B.1691. Further, the legislation requires the Department to host a meeting to obtain recommendations from stakeholders and the public on policies and programs to accelerate energy storage system deployment to achieve the storage capacity the study determines to be required. The purpose of the contract was to fulfill the report and engagement requirements mandated by legislation.
Project Duration
Tue, 12/05/2023 - 00:00
Sun, 03/31/2024 - 00:00
Sun, 03/31/2024 - 00:00
Yes
{Empty}
Contract Amounts
$193399.00
$0
$161553.50
Yes
Funding for this contract was provided by the Minnesota Legislature’s budget appropriations for fiscal years 2024 and 2025.
No
N/A
Laura Lyons
laura.lyons@state.mn.us
The schedule for this contract was very tight to meet legislated deadlines. The contractor either met the timeline objectives established at contract initiation, or they met revised timelines that were discussed between Siemens and the State as the project progressed. Deliverables were completed within the established project dates.
Acceptable. Portions of the modeling, report, and engagement were very high quality. Other portions of the modeling and report needed additional clarification from staff due to unclear assumptions and model inputs. The final deliverables required a few reviews but reached a quality final product.
Very reasonable.
The contractor’s overall performance was high. This was an aggressive schedule to maintain and complex deliverables to finalize. The contractor was flexible when it was determined that the first stakeholder engagement meeting might not completely satisfy statutory requirements, so they held a second meeting that gathered valuable input. Future project managers with this contractor should ensure the contractor establishes routine check-in meetings to discuss timelines and progress of deliverables. All timelines were met, but more routine updates from the contractor could have provided additional clarity towards the end of the project.
Yes
N/A
4 - satisfied